Solar Energy
Covenant Solar Energy Facility 315 MW (Limpopo Province) (2023 - 2024):
- Development of a Feasibility Study for a PV facility with step-up substation &
132 kV dual-circuit line
- Engineering, grid study and grid connection engineering, permitting, technical inputs during acquisition
Baobab Solar Energy Facility 600 MW (Limpopo Province) (2023 - 2024):
- Development of a Feasibility Study for a PV facility with step-up substation &
132 kV dual-circuit line
- Engineering, grid study, permitting, technical inputs during acquisition
Pioneer 100 MW Solar PV and BESS (Eastern Cape Province) (2023 - 2024):
- Development of a Feasibility Study for a PV facility with step-up substation &
132 kV dual-circuit line
- Project development support, grid concept design, grid study
Wind Energy
Magwa 140 MW Wind Energy Facility
(Eastern Cape) (2022 - 2024):
- Development of a Feasibility Study for a wind facility with step-up substation & 132 kV dual circuit line
- Project development, conceptual design, grid study, grid concept design, permitting
Grid Engineering
Greenbushes 15 MW Solar Energy Facility (Eastern Cape) (2022 - 2024):
- Medium Voltage (MV) and High Voltage (HV) power evacuation component of the proposed facility
- Grid concept design, grid study and grid connection engineering, detailed design, EPC procurement, construction monitoring.Battery Storage
Boitekong BESS (North West Province) (2023 -2024)
(Awarded BESIPPPP BW2 preferred bidder status):
- Development of a 77 MW BESS project at Marang Main Transmission Substation
- End-to-end project development from project inception until shovel-readiness, including: conceptual design, grid study and grid connection engineering, managing ESIA inputs, permitting, licenses and consents, managing topographical, geotechnical and traffic impact studies, bid submission support to AMEA Power.